The appeal documents for North Court Solar Farm were published on Ashford Borough Council (ABC)'s planning portal yesterday: AP-90713
The clock has started ticking!
ABC will notify any person who was notified or consulted and those who made representations to the application will be notified that an appeal has been made. They must do this by 11 December.
Interested party comments need to be submitted by 8 January 2025! Yet another Christmas ruined - 3rd in a row!
The Planning Inspector should do a site visit at some stage.
We are working hard going through the submitted appeal documents and if anyone can lend us their time that would be most helpful! Please let me know ASAP!
When we hear anything more or can give you further advice we will let you know.